Toor, S U R and Ogunlana, S (2008) Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), pp. 395-408. ISSN 1466433X
Abstract
Delays are frequent and recurring in construction projects in developing countries. Although the principal reasons for construction delays are comparable across developing countries, several factors pertaining to local industry, socio-economic and cultural issues and project characteristics also contribute to construction delays. Questionnaire surveys and interviews were conducted on a major construction project in Thailand to explore the most significant problems causing construction delays. Factors related to designers, contractors and consultants were rated among the top problems. Issues such as lack of resources, poor contractor management, shortage of labour, design delays, planning and scheduling deficiencies, changed orders and contractors' financial difficulties were also highlighted during the interviews. Notably, problems such as 'multicultural and multilingual environment causing ineffective communication', 'large number of participants of project' and 'involvement of several foreign designers and contractors' were rated among the bottom 10 problems in the 75-item problem inventory. These findings can be helpful for project managers to mitigate the construction delays in Thailand. In order to effectively overcome the construction delays in developing countries, suggestions are made for fundamental and large-scale reforms in procurement systems, value chain management and stakeholders' management.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | delays; developing country; major projects; Thailand |
| Index terms: | questionnaire, construction project, construction delay, survey, scheduling, developing country, interview, Thailand, procurement system, designer, major project, project manager, inventory, value chain |
| Subjects: | project controls, development economics, value chain strategy, inventory management, Geography, production management, operations research, strategic project management, contractual arrangements, profession, data collection methods |
| Topics: | Geographical Context, Project Management, Research Practice, Procurement, Roles and Professions, International Construction, Supply Chain Management, Time Control |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here