Subcontract and supply enquiries in the tender process of contractors

Laryea, S (2009) Subcontract and supply enquiries in the tender process of contractors. Construction Management and Economics, 27(12), pp. 1219-1230. ISSN 1466433X

Abstract

In the tender process, contractors often rely on subcontract and supply enquiries to calculate their bid prices. However, this integral part of the bidding process is not empirically articulated in the literature. Over 30 published materials on the tendering process of contractors that talk about enquiries were reviewed and found to be based mainly on experiential knowledge rather than systematic evidence. The empirical research here helps to describe the process of enquiries precisely, improve it in practice, and have some basis to support it in theory. Using a live participant observation case study approach, the whole tender process was shadowed in the offices of two of the top 20 UK civil engineering construction firms. This helped to investigate 15 research questions on how contractors enquire and obtain prices from subcontractors and suppliers. Forty-three subcontract enquiries and 18 supply enquiries were made across two different projects with average value of £7m. An average of 15 subcontract packages and seven supply packages was involved. Thus, two or three subcontractors or suppliers were invited to bid in each package. All enquiries were formulated by the estimator, with occasional involvement of three other personnel. Most subcontract prices were received in an average of 14 working days; and supply prices took five days. The findings show 10 main activities involved in processing enquiries and their durations, as well as wasteful practices associated with enquiries. Contractors should limit their enquiry invitations to a maximum of three per package, and optimize the waiting time for quotations in order to improve cost efficiency.

Item Type: Article
Uncontrolled Keywords: case study; enquiries; subcontractors; suppliers; UK
Index terms: observation, bidding, subcontractor, duration, evidence, estimator, package, subcontract, tendering process, construction firm, case study, personnel, cost efficiency
Subjects: project controls, profession, management, bidding, economics, organization, contractual arrangements, practitioner, data collection methods, evaluation and assessment methods, tendering, contract type
Topics: Business Strategy, Procurement, Cost Management, Contract Administration, Human Resources, Research Practice, Time Control, Roles and Professions
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here