Jensen, D A (2010) A longitudinal study of a Type I differing conditions claim: Investigating the contractor's failure to meet the reasonable prudent standard. Construction Management and Economics, 28(1), pp. 63-74. ISSN 1466433X
Abstract
The United States government's differing conditions clause poses extensive legal and financial risk. This contract clause addresses Type I and Type II unforeseen conditions. A Type I condition occurs when a latent physical condition materially differs from that condition indicated in the bidding documents. A Type II condition exists when an unknown physical condition has an unusual nature different from that condition generally encountered and naturally inhering in the contract work. The occurrence of either provides a contractor with the contractual right to file a claim for equitable contract adjustment. A contractor desiring to prevail, regarding a Type I claim, must properly comply with the Weeks Dredging proof elements. Chi-square statistical results, for 143 Type I differing conditions claims, provide empirical evidence that 79% of the contractors receive a disfavourable court award when challenging the United States government. Forty-four per cent of the reported cases cite the Weeks Dredging proof element, contractor did not act as a reasonably prudent contractor, as a basis for denying a contractor's claim for equitable adjustment. This standard measures whether a reasonable contractor did or did not review and properly document all bidding documents.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | bidding; contract claims; government contracts; site conditions; type i claim |
| Index terms: | contract claim, bidding, dredging, documents, evidence, United States |
| Subjects: | evaluation and assessment methods, bidding, water management, Geography, professional development, payment |
| Topics: | Geographical Context, Research Practice, Information Management, Procurement, Sustainability, Contract Administration |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here