Time-cost relationship of building projects: Statistical adequacy of categorization with respect to project location

Dursun, O and Stoy, C (2011) Time-cost relationship of building projects: Statistical adequacy of categorization with respect to project location. Construction Management and Economics, 29(1), pp. 97-106. ISSN 1466433X

Abstract

Construction duration is one of the key elements to determine the success of a project. Several models have been developed to provide precise predictions of construction duration. The datasets in previous studies comprise observations from particular countries. This precludes examination of the role of project location at the country level for modelling construction duration. The aim, therefore, is to test the statistical adequacy of categorizing projects with respect to their locations for modelling construction duration. A formal procedure to evaluate the adequacy of categorizing observations is also presented. It is intended to contribute to the epistemology of modelling construction duration. The dataset was generated from a global client. It contains information on 246 projects from 25 different countries. This creates a categorical variable for location. Bromilow's time-cost model is chosen to assess the adequacy of this categorization. A full model with indicator and interaction variables is compared to a restricted one. Parameter estimation was performed according to the ordinary least squares method. F-statistics are calculated and the probability of the value is significant. The results show that two distinct groups with substantial changes in model parameters exist in the dataset. It is also noted that conclusions are valid over the selected population.

Item Type: Article
Uncontrolled Keywords: bromilow's time-cost model; categorization; f-ratio; project location
Index terms: population, parameter-estimation, dataset, time-cost model, interaction, modelling, duration, statistics, epistemology
Subjects: behavioral psychology, statistical analysis, demography, project controls, data management, quantity surveying, analytical methods, knowledge theory, mathematical modelling
Topics: Engineering Principles, Research Practice, Risk Management, Urban Studies, Digital Applications, Time Control
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here