Challenges and opportunities for productivity improvement studies in linear, repetitive, and location-based scheduling

Lucko, G; Alves, T D C L and Angelim, V L (2014) Challenges and opportunities for productivity improvement studies in linear, repetitive, and location-based scheduling. Construction Management and Economics, 32(6), pp. 575-594. ISSN 01446193

Abstract

Despite theoretical advancements in alternative project planning methods the extent of their practical implementation varies strongly; it has been limited especially in the US construction industry. The family of linear, repetitive, and location-based scheduling techniques holds significant but barely substantiated promise by containing multiple variables of interest for integrated analysis and optimization. Yet it is necessary to provide empirical evidence that using such techniques can improve productivity to increase credibility and acceptance by practitioners, because claims of conceptual superiority are only sporadically supported with detailed measures. An analysis is performed to identify relevant decision-making variables, extract challenges that currently limit the corpus of quantitative productivity studies on alternative scheduling to its insufficient size, and reveal opportunities to expand it in breadth and depth. Variables are categorized by their relevance to time, activity, resource and location, as well as the managerial approach. Challenges include the diverse definitions of productivity itself, issues related to achieving generalizability, and the detailed steps of data collection, preparation, and analysis. Opportunities include the guidance from existing but rare studies and well-established research methods such as case studies that can be applied. This is illustrated with a sample project of a high-rise apartment building in Brazil. If alternative methods can be proven to be measurably better for specific applications, there might be a paradigm shift from merely defaulting to traditional but problematic network-based scheduling toward consciously choosing the planning method based on its potential benefits for a project.

Item Type: Article
Uncontrolled Keywords: case studies; project management; project planning; scheduling; workflow
Index terms: decision-making, evidence, practitioner, workflow, project planning, scheduling, Brazil, apartment building, paradigm, construction industry, implementation, project management, planning method, case study, productivity
Subjects: decision analysis, industry analysis, management, education and knowledge transfer, Geography, project management theory and practice, urban planning, operations research, contractual arrangements, construction type, data collection methods, evaluation and assessment methods, control systems, practitioner
Topics: Risk Management, Roles and Professions, Governance, Procurement, Construction Technology, Business Strategy, Research Practice, Project Management, Geographical Context, Time Control
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here