Enhanced heuristic for finance-based scheduling of construction projects

Gajpal, Y and Elazouni, A (2015) Enhanced heuristic for finance-based scheduling of construction projects. Construction Management and Economics, 33(7), pp. 531-553. ISSN 01446193

Abstract

Typically, construction contractors operate under cash-constrained operating conditions. The lag between the time when contractors spend money to accomplish work on site and the time when payments are actually made by clients, which partially compensate contractors for the accomplished work, constantly creates a finance deficit. Contractors often supplement finance deficits using external funds procured through establishing credit-line bank accounts which typically allow contractors to withdraw cash up to specified credit limits. This makes the task of project scheduling considering the constraints of specified finance very important for financial and operational planning. This scheduling concept and technique are referred to as finance-based scheduling. An enhanced heuristic is proposed to devise finance-based schedules of multiple projects within contractors' portfolios. The enhancement is achieved by replacing the exhaustive enumeration technique employed in the heuristic to specify activities' start times with a polynomial shifting algorithm. This enhancement resulted in a substantial reduction in the number of solutions explored before a feasible solution is encountered. The enhanced heuristic was validated through comparison with the integer programming technique using 240 problems of randomly generated networks of sizes that range from 30 to 240 activities. Further, it was proved that the enhanced heuristic can be easily scaled up to handle portfolios of multiple large-size projects.

Item Type: Article
Uncontrolled Keywords: cash flow management; financial planning; heuristic; project finance; scheduling
Index terms: construction project, heuristic, integer programming, project finance, scheduling, cash flow management, project scheduling, financial planning, construction contractor
Subjects: risk assessment, operations research, financial management, practitioner, project controls, financial and cost management, algorithms, production management
Topics: Cost Management, Digital Applications, Risk Management, Project Management, Roles and Professions, Time Control
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here