Construction flow index: A metric of production flow quality in construction

Sacks, R; Seppänen, O; Priven, V and Savosnick, J (2017) Construction flow index: A metric of production flow quality in construction. Construction Management and Economics, 35(1-2), pp. 45-63. ISSN 01446193

Abstract

A new, process-oriented approach is needed in construction management. Lean construction emphasizes the concept of flow as a way to understand production in construction, yet there is still no accepted metric for measurement of flow quality. This has hampered research and practice. The proposed construction flow index (CFI) is a composite measure that reflects the quality of production flow in repetitive construction projects. It incorporates measures of work continuity for crews, processing continuity for locations, production rate variation, amounts of work in progress, interference and operation sequence logic. Expert knowledge was acquired to establish weights for the CFI parameters, and its use was tested in evaluating the planned and actual production flows for a number of projects. Project managers can use the CFI to evaluate the quality of their construction plans and to measure and communicate production flow quality status to trade crews, enabling management and improvement of production flow. The CFI is also a valuable tool for construction research. The CFI challenges traditional construction management by measuring flow, where standard practice only measures transformation (earned value). It challenges lean construction practice using the Last Planner System, suggesting that the percent plan complete measure of plan reliability is insufficient.

Item Type: Article
Uncontrolled Keywords: building industry; lean construction; production process; workflow
Index terms: building industry, percent plan complete, traditional construction, project manager, composite, transformation, last planner system, variation, workflow, lean construction, repetitive construction, production process
Subjects: management, manufacturing engineering, contractual condition, project controls, building construction, heritage and conservation, industry analysis, profession, business, materials science
Topics: Contract Administration, Time Control, Site Management, Design Practice, Construction Technology, Roles and Professions, Engineering Principles, Construction Materials, Research Practice, Business Strategy
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here