Ballesteros-Pérez, P; Smith, S T; Lloyd-Papworth, J G and Cooke, P (2018) Incorporating the effect of weather in construction scheduling and management with sine wave curves: Application in the United Kingdom. Construction Management and Economics, 36(12), pp. 666-682. ISSN 01446193
Abstract
The impact of (adverse) weather is a common cause of delays, legal claims and economic losses in construction projects. Research has recently been carried out aimed at incorporating the effect of weather in project planning; but these studies have focussed on either a narrow set of weather variables, or a very limited range of construction activities or projects. A method for processing a country’s historical weather data into a set of weather delay maps for some representative standard construction activities is proposed. Namely, sine curves are used to associate daily combinations of weather variables to delay and provide coefficients for expected productivity losses. A complete case study comprising the construction of these maps and the associated sine waves for the UK is presented along with an example of their use in building construction planning. Findings of this study indicate that UK weather extends project durations by an average of 21%. However, using climatological data derived from weather observations when planning could lead to average reductions in project durations of 16%, with proportional reductions in indirect and overhead costs.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | climate; construction; project delay; schedule; weather |
| Index terms: | duration, productivity, construction activity, construction scheduling, case study, weather, project planning, project delay, construction project, United Kingdom, building construction, maps |
| Subjects: | air quality, data collection methods, control systems, construction operations, spatial and geospatial analysis, management, production management, Geography, building construction, project controls |
| Topics: | Time Control, Site Management, Business Strategy, Research Practice, Project Management, Geographical Context, Sustainability, Construction Technology |
| Descriptive scope: | 3 PCE |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here