A novel multiple linear regression model for forecasting S-curves

Blyth, K and Kaka, A (2006) A novel multiple linear regression model for forecasting S-curves. Engineering, Construction and Architectural Management, 13(1), pp. 82-95. ISSN 0969-9988

Abstract

Purpose - Cash flow forecasting is an indispensable tool for construction companies, and is essential for the survival of any contractor at all stages of the work. A simple and fast technique of forecasting cash flow accurately is required, considering the short time available and the associated cost. Seeks to examine this issue. Design/methodology/approach - The paper argues that instead of producing an S-curve that is based on historical projects combined (state-of-the-art is based on classifying projects into groups and producing a standard curve for each group simply by fitting one curve into the historical data), here the attempt is to produce an individual S-curve for an individual project. A sample of data from 50 projects was collected and 20 criteria were identified to classify these projects. Using the most influential criteria, a multiple linear regression model was created to forecast the programme of works and hence the S-curves. A further six projects were used to validate and test the model. Findings - The results of the model developed in this paper were compared with previous models and evaluated. It is concluded that the model produced more accurate results than existing value and cost models. Originality/value - The paper proposes an alternative and novel approach to the development of standard value and cost commitment S-curves. This approach is based on a multiple linear regression model of the programmes of works.

Item Type: Article
Uncontrolled Keywords: cash flow; construction industry; financial forecasting; project management
Index terms: s-curve, project management, cash flow forecasting, survival, construction industry, forecasting, regression model, state of the art, cost model, methodology, cash flow, programme, construction company, commitment
Subjects: psychology, financial and cost management, prediction and forecasting, environmental science, organization, research dissemination and communication, project controls, statistical analysis, industry analysis, research methods, economics, financial management, project management theory and practice
Topics: Sustainability, Research Practice, Project Management, Cost Management, Business Strategy, Time Control, Organizational Design
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here