The significant factors causing delay of building construction projects in Malaysia

Alaghbari, W; Kadir, M R A and Salim, A (2007) The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), pp. 192-206. ISSN 0969-9988

Abstract

Purpose - The paper seeks to identify the major factors causing delay in building construction projects in Malaysia. Design/methodology/approach - A questionnaire survey was used to carry out the study. The questionnaire consisted of 31 factors which were grouped into four major categories by responsibility - contractor factors, owner factors, consultant factors and external factors. The level of importance of the categories was measured and the relative importance of weights was ranked. Findings - The study finds that financial problems are the main factor and coordination problems are the second most important factor causing delay in construction projects in Malaysia. The results were analyzed to rank the causes of delay and further classify the types of delay. Research limitations/implications - The scope of this study is limited to building projects in the Klang Valley area, where major Malaysian cities such as Kuala Lumpur, Putrajaya, Petaling Jaya, Shah Alam and Seremban are located. The data for this study was gathered through a detailed questionnaire survey. Originality/value - Based on the analysis of the ranking and intensity of causes of delay, this paper suggests possible improvements that could be made in order to reduce delays in the construction industry.

Item Type: Article
Uncontrolled Keywords: construction industry; Malaysia; project management
Index terms: methodology, construction project, questionnaire, relative importance, building construction, survey, causes of delay, construction industry, project management, coordination, Malaysia, owner
Subjects: industry analysis, building construction, sociology, project controls, project management theory and practice, production management, Geography, research methods, management, data collection methods, risk assessment
Topics: Construction Technology, Stakeholder Management, Risk Management, Geographical Context, Project Management, Research Practice, Organizational Design, Time Control
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here