Oo, B L; Drew, D and Lo, H (2007) Modelling contractors' mark-up behaviour in different construction markets. Engineering, Construction and Architectural Management, 14(5), pp. 447-462. ISSN 0969-9988
Abstract
Purpose - In order to compete successfully, international contractors need to have an understanding not only of the make-up of the different competitive environments within each country, but also of contractors' competitive behaviour within those environments. Contractors' mark-up decision making in public sector contracting is directly compared in two construction markets - Hong Kong and Singapore. Design/methodology/approach - Regression analysis is used to compare the lowest percentage mark-up in both markets against four mark-up decision factors that fall into two groups - market-environment factors (i.e. number of bidders, market conditions) and project-specific factors (i.e. type and size of project). Data were gathered using a designed bidding experiment. Findings - In line with de Neufville et al.'s "good year-bad year" study, the effect of market conditions was found to be independent of the number of bidders in both markets; contractors' mark-up decreases as the number of bidders increases, with lower mark-up in recession. In addition, this study provides evidence that contractors' mark-up behaviour varies in different markets: Hong Kong contractors' mark-up behaviour is more straightforward, in that only the market-environment factors are significant. However, Singapore contractors' mark-up behaviour is affected by project type in addition to the market-environment factors. Project size was not found to be significant in either market. Originality/value - The empirical findings provide a valuable insight into contractors' mark-up behaviour, especially those contractors intending to bid for jobs in these two internationally renowned construction markets.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction industry; Hong Kong; mathematical modelling; Singapore; tendering |
| Index terms: | experiment, market condition, number of bidders, mark-up, bidding, evidence, methodology, decision-making, public sector, recession, Singapore, Hong Kong, construction market, regression analysis, modelling, construction industry, markets, mathematical modelling |
| Subjects: | economic and policy analysis, data collection methods, evaluation and assessment methods, analytical methods, economic analysis, bidding, Geography, research methods, price determination, statistical analysis, administrative law, industry analysis, decision analysis, market analysis |
| Topics: | Risk Management, Procurement, Business Strategy, Geographical Context, Research Practice, Engineering Principles, Legal Issues |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here