Risk stages and factors in architectural design- a structural equation modelling

Tabarroki, S; Nazari, A and Banihashemi, S (2024) Risk stages and factors in architectural design- a structural equation modelling. Architectural Engineering and Design Management, 20(1), pp. 79-101. ISSN 1745-2007

Abstract

ABSTRACTThe design phase is one of the key project processes in the construction industry. Despite the architects' responsibility to develop complete, accurate and coordinated project documents, architectural design is accompanied by multiple errors and consequential risks. That is, the errors are potentially costly and time-consuming to correct and impose significant risks if are not caught early during the design phase, and become cumbersome to be handled in the construction documents and the construction phase. The aim of this research is to identify the risky stages in the architectural design process and find what factors cause risks in that process within the context of Iran. To this end, a combination of a qualitative and quantitative method as the sequential mixed-method was designed in which the research was commenced through the qualitative exploratory investigation to discover the literature and then, proceeded to the quantitative research including questionnaire design, model structure development and the Partial Least Square Structural Equation Modelling (PLS-SEM) application and analysis. The results of the study reveal that the greatest design risks may occur in the identification and investigation phase of the Iranian architectural design process when the feasibility studies and planning are not conducted accurately, correctly and completely. Moreover, the outcome shows that time pressures in design data collection, ambiguous objectives of the clients, and poor disciplinary coordination are the main risk factors in architectural design.

Item Type: Article
Uncontrolled Keywords: Architecture; Design process; architectural design; design error; risk modelling; construction projects; Construction industry; Architectural design; Feasibility studies; Modelling; Documents; Data collection; Risk factors; Errors; Design factors; Quantitative analysis; Quantitative research
Index terms: construction phase, quantitative analysis, design factor, construction industry, partial least square, modelling, coordination, architectural design, construction project, questionnaire, investigation, quantitative method, design risk, design phase, risk factor, documents, architect, structural equation modelling, feasibility study, design error, quantitative research, design process
Subjects: industry analysis, statistical analysis, environmental hazards, production management, financial risk, professional development, management, design practice, data analysis and analytics, professional practice, project delivery, analytical methods, design stages, design methods, profession, data collection methods
Topics: Design Practice, Organizational Design, Cost Management, Engineering Principles, Information Management, Project Management, Research Practice, Roles and Professions, Sustainability
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here