Resource levelling optimization model considering float loss impact

El-Sayegh, S (2018) Resource levelling optimization model considering float loss impact. Engineering, Construction and Architectural Management, 25(5), pp. 639-653. ISSN 0969-9988

Abstract

Purpose: The purpose of this paper is to propose a Non-Linear Integer Programming (NLIP) model that solves the resource leveling problem while reducing the negative effect of the total float loss on risk. Design/methodology/approach: An NLIP model is formulated to solve the resource leveling optimization problem incorporating float loss cost (FLC). The proposed model is implemented using “What’s Best solver” for Excel. The FLC is calculated using the float commodity approach. An example is solved using the proposed model in order to illustrate its applicability. Sensitivity analysis is also performed. Findings: The results confirmed that resource leveling reduces the available float of non-critical activities; decreases schedule flexibility and reduces the probability of project completion. The probability of timely completion dropped from 50 percent (for the normal schedule with 32 resource fluctuations) to 13.5 percent for leveled resources with zero fluctuations. Using the proposed method, the number of resource fluctuations is 8 but the probability of completing the project on time improved to 20 percent. Practical implications: The proposed model allows project managers to exercise new trade-offs between resource leveling and schedule flexibility which will ultimately improve the chances of successful project delivery. Originality/value: Resource leveling techniques result in reducing the available total float for the non-critical activities. Existing methods focus on moving noncritical activities within their available float and ignore the impact of the resulting float loss. This reduces the schedule flexibility and increase the risk of project delays. The proposed model incorporates the FLC into the resource leveling optimization problem resulting in more efficient schedules with improved resource utilization while keeping some schedule flexibility.

Item Type: Article
Uncontrolled Keywords: construction management; project management; scheduling
Index terms: methodology, project delay, scheduling, sensitivity analysis, resource levelling technique, project management, integer programming, project delivery, exercise, project manager, resource utilization, resource levelling
Subjects: operations research, resource management, site logistics, project delivery, profession, health behaviours and lifestyles, project controls, environmental hazards, research methods, algorithms, project management theory and practice
Topics: Procurement, Sustainability, Roles and Professions, Project Management, Research Practice, Health and Safety, Site Management, Time Control, Digital Applications
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here