Du, J; Wang, Q and Shi, Q (2019) Description-experience gap under imperfect information: Information continuum and aggressive cost estimating in capital projects. Engineering, Construction and Architectural Management, 26(6), pp. 1151-1170. ISSN 0969-9988
Abstract
Purpose: Capital project delivery, such as the delivery of transportation networks and industrial facilities, often suffers losses due to overly aggressive planning. Planners often are overly optimistic about the chance of success while underestimating risks. The purpose of this paper is to examine the hypothesis that these biases are from the difficulties most decision makers face when interpreting probabilistic information. Design/methodology/approach: Three behavioral experiments were conducted to test the theoretical fitness of the paradigms proposed by the description–experience gap literature, namely, the sampling errors effect, the recency effect and statistical information format. College students were recruited to participate in a series of estimating tasks. And their estimating results were compared given different levels of information completeness. Findings: It was found that the existing paradigms could predict risk decision making in the risk-averse estimating scenarios where test subjects were required to give a relatively conservative estimate, but they seemed to be less effective in predicting decisions in the risk-seeking estimating scenario, where test subjects were asked to give a relatively aggressive estimate. Originality/value: Based on these findings, an integrative model is proposed to explain the observations pertaining to aggressive planning in capital projects. Two dimensions are deemed to be relevant: including risk-taking intentions, and an information uncertainty continuum that ranges from an implicit experience-based information representation to an explicit description-based information representation.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction planning; decision support systems; estimating |
| Index terms: | college student, construction planning, estimate, dimension, planner, sampling, paradigm, capital project, experiment, face, cost estimating, decision support, risk taking, estimating, bias, methodology, decision-making |
| Subjects: | data collection methods, profession, psychology, financial and cost management, strategic project management, health monitoring assessment and metrics, construction planning, decision-making and reasoning, research methods, education and knowledge transfer, probability and distributions, decision analysis, sociology |
| Topics: | Site Management, Organizational Design, Risk Management, Roles and Professions, Stakeholder Management, Research Practice, Project Management, Health and Safety, Cost Management |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here