Salama, T and Moselhi, O (2019) Multi-objective optimization for repetitive scheduling under uncertainty. Engineering, Construction and Architectural Management, 26(7), pp. 1294-1320. ISSN 0969-9988
Abstract
Purpose: The purpose of this paper is to present a newly developed multi-objective optimization method for the time, cost and work interruptions for repetitive scheduling while considering uncertainties associated with different input parameters. Design/methodology/approach: The design of the developed method is based on integrating six modules: uncertainty and defuzzification module using fuzzy set theory, schedule calculations module using the integration of linear scheduling method (LSM) and critical chain project management (CCPM), cost calculations module that considers direct and indirect costs, delay penalty, and work interruptions cost, multi-objective optimization module using Evolver © 7.5.2 as a genetic algorithm (GA) software, module for identifying multiple critical sequences and schedule buffers, and reporting module. Findings: For duration optimization that utilizes fuzzy inputs without interruptions or adding buffers, duration and cost generated by the developed method are found to be 90 and 99 percent of those reported in the literature, respectively. For cost optimization that utilizes fuzzy inputs without interruptions, project duration generated by the developed method is found to be 93 percent of that reported in the literature after adding buffers. The developed method accelerates the generation of optimum schedules. Originality/value: Unlike methods reported in the literature, the proposed method is the first multi-objective optimization method that integrates LSM and the CCPM. This method considers uncertainties of productivity rates, quantities and availability of resources while utilizing multi-objective GA function to minimize project duration, cost and work interruptions simultaneously. Schedule buffers are assigned whether optimized schedule allows for interruptions or not. This method considers delay and work interruption penalties, and bonus payments.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | optimization; scheduling; uncertainty |
| Index terms: | duration, multi-objective optimization, module, buffer, productivity, fuzzy set theory, critical chain project management, indirect cost, integration, methodology, linear scheduling, cost optimization, repetitive scheduling, genetic algorithm, penalty, scheduling |
| Subjects: | economics, algorithms, research methods, management, architectural elements, financial risk, project controls, organizational analysis, cost management, regulatory law, decision-making and optimization, operations research |
| Topics: | Procurement, Research Practice, Business Strategy, Cost Management, Time Control, Organizational Design, Digital Applications, Legal Issues, Design Practice |
| Descriptive scope: | 3 PCT |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here