Exploring the missing link between top management team characteristics and megaproject performance

Yun, L; Wan, J; Wang, G; Bai, J and Zhang, B (2020) Exploring the missing link between top management team characteristics and megaproject performance. Engineering, Construction and Architectural Management, 27(5), pp. 1039-1064. ISSN 0969-9988

Abstract

Purpose: The purpose of this paper is to analyze the relationship between the demographic characteristics of top management teams (TMTs) (i.e. age, gender, administrative level, senior management experience and educational background) and megaproject performance, with respect to schedule, cost, quality, safety and technological innovation. The results shed new light on the effectiveness of different types of TMT. Design/methodology/approach: This paper collected secondary and objective data from 208 TMT members in 42 megaprojects and employed hierarchical regression analysis to test the research hypotheses. Findings: The findings revealed that age has a significant influence on schedule performance; gender has a significant influence on safety performance; senior management experience has a significant influence on cost performance; and educational background has a significant influence on both schedule and technological innovation performance. However, this study did not find evidence of a significant relationship between the administrative level and megaproject performance. Research limitations/implications: This paper mainly focused on China’s megaprojects, most of which are globally influential (e.g. Hong Kong–Zhuhai–Macao Bridge and Shanghai Expo), however this sampling approach still limits the generalizability of research findings to other contexts. Originality/value: The results of this paper contribute to a better understanding of how management team capabilities translate into better project achievements. This paper also provides implications on the criteria for selecting top megaproject managers to optimize the composition of the TMT and realize better performance.

Item Type: Article
Uncontrolled Keywords: construction; organization; project management
Index terms: Shanghai, manager, schedule performance, China, safety performance, cost performance, megaproject, top management team, methodology, evidence, Hong Kong, regression analysis, project management, effectiveness, technological innovation, sampling
Subjects: evaluation and assessment methods, data collection methods, practitioner, strategic project management, innovation and technology management, research methods, economics, performance management, management, project management theory and practice, Geography, occupational health and safety management, project controls, statistical analysis
Topics: Time Control, Organizational Design, Quality Management, Roles and Professions, Engineering Principles, Research Practice, Geographical Context, Project Management, Health and Safety, Cost Management
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here